As we read in our specifications, that prepared the day before the assembly, the House stand is, we thought it was a funny mistake. Who will have the first frame and then the house .... EBH does that, we were amazed when we came on the eve of the plot and our bottom plate was surrounded suddenly.
clock rang at 07.30 the next morning my phone - it was someone from EBH - lack of site electricity. Somehow it missed the city works to incorporate also a counter in the counter column. Exclusive in Potsdam one thing: a normal construction sites is not - here is the column count prescribed. I could not help with the problem but I promised the short term to appear on the site. Here the sight on our arrival. We have blocked the road as a precaution and so the truck could stand alone and can be discharged. Here is number one ....
... and a little further down the road we have seen four others.
on the property paid for our expensive 70-tonne crane had moved into position. Actually, here is a 30 ton used copy, because the truck but not even fit on the property, the long road between the road and bridge building had now so be.
The first two walls, we have missed. The excitement and joy is still on a high note.
Many busy hands. The installation team worked impressively efficient. Obviously everyone knows what to do, because there was only a few commands and all looked always more than busy. As a layman difficult to assess but it was not yelling across the square and there was never hurried. For us, a sign that nothing unexpected happened. The site electricity has EBH fix organized by the neighbors (thank you!). A few hours later was the official box connected and operational. Where exactly it is clamped, I can not say but the result counts.
one wall after another has now been unloaded and assembled. All walls have apparently fit well, because by noon the ground was already installed.
Missy, which could otherwise already registered every stranger on the property and loudly indicating their territory, in view of the many people and machines, just stand amazed.
Later, you have - even in the largest construction site noise - usually placed as:
fact, our house ... and even written entirely correct. Enthusiasm is spreading.
The last wall in the ground floor was closed ...
... so we could perform a short time later, a first offense. The I-Team EBH us directly carried out again and we are the location of outlets and switches went through again. We still have to change something and we have also done this just before close.
the afternoon, the ceiling was flown - here's a piece with the stair section.
Even a few walls of the attic were already installed - to be exact, almost all and we are still on the first day! Impressive, what with good preparation and planning, shall pass.
Shortly before closing time I had another look into the closed house thrown. My father (still slightly skeptical regarding the design) is in the next few days to visit and helps busy with many side projects and is also the first time in the future our living room.
After more than twelve hours working through the house covered with huge tarps. While it is absolutely no rain announced but is certainly better and I think also good. The workers have cleaned up the site yet and we have adopted for that day too.
Day 2:
morning in addition to the components for the roof also all other building materials were unloaded. The last two trucks had tile, lots of wood and insulation material loaded. In the early afternoon, the crane was ready and went back to his homeland. The installation team had now apparently all hands full to build the roof. Until the evening, pounding like crazy and at the end of the day was the roof installed. We were so busy that we totally forgot to take pictures. My father kept us fully up to speed, after all, we want to mount the first part of the fence. On this occasion I made the acquaintance of a cutter - this is developing into our defense boar from steel mesh, which we kindly receive from EBH.
Linda had to work too and here marked the locations for the fence posts.
three pieces we have only managed . This was due to the particular soil structure. complicate thick as an arm roots and huge stones are extremely drilling holes in the ground. In addition, trees were here had to get in the way that will be struck down in the short term. Lots to do but the project house has really a first peak ... it must be achieved are happy with us.