Hello readers,
here is a quick update of last week:
- On Tuesday we took our two Bautockner in holding and that the "dehumidify" out now on. On
- Donnerstaf and Friday, the company Grünwald connected and that the EWP Estrichaufheizprogramm started. This will run two weeks and is powered completely on electricity. Then we get our heat then on the ground probes.
- In parallel, the ground probes inserted into the utility room and the land was transformed to its original state.
- Fischer has set on Friday the second transfer shaft, so that now all the house and drainage connections available and we are now totally independent of the weather.
- On Saturday we went to IKEA and have you ever laminate, sinks, faucets, etc. purchased. That's
During the week there will also once again a picture update ...