finished cleaning!
Hello readers,
the owner can not sleep, so it is on 2 Christmas Day, even a small update.
The cleaners are on with their work 23.12. become ready. We are very satisfied with the work. The client leaves the house every day since the 2x to properly ventilate. During the day we also put on some windows tilt and let the heater 24 / 7 . Run So the whole thing dries very well. In the first week of January, it then proceeds with the drywall II. Then, the sheet-rock in the floor and mounted ausgbebessert minor deficiencies in the vapor barrier sheet.
One thing I noticed yesterday: added to the windows on the upper floor there any white mass liquefied. Now I know not whether the sealant or adhesive, and hope that it does not affect the air tightness of the windows. Does anyone have any idea how, why and why this happened? Let's see if our BL can be reached on Monday ...
Saturday, December 25, 2010
Tuesday, December 21, 2010
Hundreds Of Itchy Bumps On Stomach
is
Hello readers,
, the use at the weekend paid off. The interior walls in the house have a temperature of 14 ° C and 18 ° C and runs the building water. On Sunday evening we had in Bad Oldesloe -13 ° C, although the water bubbled up on Monday morning without any problems from the tap. The box is really worth! The cleaner our homework we have done and the guys can work ... they do this since Monday also:
The nice guys of the plaster Union GmbH fill in you right now the big gaps in the filigree top and set them forth so that it ready for painting is. The charge we have directly settled with the company and the developer is really happy that he has to do not later. Until Friday (!) Noon they want to be ready for us. Let's see if they do that.
Hello readers,
, the use at the weekend paid off. The interior walls in the house have a temperature of 14 ° C and 18 ° C and runs the building water. On Sunday evening we had in Bad Oldesloe -13 ° C, although the water bubbled up on Monday morning without any problems from the tap. The box is really worth! The cleaner our homework we have done and the guys can work ... they do this since Monday also:
| |
| for a small fee we can plaster the same filigree ceiling painters finished. |
The nice guys of the plaster Union GmbH fill in you right now the big gaps in the filigree top and set them forth so that it ready for painting is. The charge we have directly settled with the company and the developer is really happy that he has to do not later. Until Friday (!) Noon they want to be ready for us. Let's see if they do that.
Saturday, December 18, 2010
Vegeta Bluma Doujinshi
cleaning and sanitation
Hello Readers,
the past week was very successful. Our Lord Eletrik Dörbandt has concluded with his boys pre-installation. On Thursday it was also the company Roland Green forest with us and has the Sanitärvorinstallation completed in a day. These parts also has a good reason ... at the current Monday the cleaners do join us, yay!
this purpose, the client got a little "homework". I'm supposed to do on Sunday night our heater again, that we get a little temperature in the house. The Inennenwände have come around to +4 ° C. Let's see if our house is well insulated really well.
The second task is to provide running water, at the current temperatures no easy task. Here I have taken up a grandiose idea of Azar and constructed with OSB boards, a small hut by the water supply. This is a 60W bulb and is insulated with rock wool. The lamp makes a beautiful warmth and the water does not freeze anymore.
Here now some pictures of work from last week:
And here are some winter photos in stone fields Redder:
Hello Readers,
the past week was very successful. Our Lord Eletrik Dörbandt has concluded with his boys pre-installation. On Thursday it was also the company Roland Green forest with us and has the Sanitärvorinstallation completed in a day. These parts also has a good reason ... at the current Monday the cleaners do join us, yay!
this purpose, the client got a little "homework". I'm supposed to do on Sunday night our heater again, that we get a little temperature in the house. The Inennenwände have come around to +4 ° C. Let's see if our house is well insulated really well.
The second task is to provide running water, at the current temperatures no easy task. Here I have taken up a grandiose idea of Azar and constructed with OSB boards, a small hut by the water supply. This is a 60W bulb and is insulated with rock wool. The lamp makes a beautiful warmth and the water does not freeze anymore.
| |
| The "water hut |
| |
| heat source: 60W incandescent |
Here now some pictures of work from last week:
| |
| bedroom |
| |
| view towards bedroom floor |
| |
| staircase |
| |
| Nursery 1 |
| |
| children a sight corridor |
| |
| store room floor |
| |
| installation wall bathroom floor |
| |
| toilet corner bathroom floor |
| |
| vent bathroom floor |
| |
| shower bathroom floor |
| |
| Here comes the tub out |
| |
| Sat cable (left) and TV connection kitchen (right) |
| |
| water supply kitchen |
| |
| cable channel for TV, electricity 2xSat, and 2x Cat |
| |
| cable salads HWR |
| |
| water supply guest bathroom |
| |
| kitchen electrics |
| |
| Steckoden in all the window frames |
| | ||
| threaded rods and cables for satellite boom | | |
Thursday, December 16, 2010
Amscot Mastercard Has Checking And Routing Number
tiles
The tiler appear with the heating contractor / plumbing trades to work in parallel. It's been exciting to see how the elements in the samples slowly coming to and from the house. Always with the thought in mind: "Hoffentlicht it looks really as good as we had imagined"
The tiler appear with the heating contractor / plumbing trades to work in parallel. It's been exciting to see how the elements in the samples slowly coming to and from the house. Always with the thought in mind: "Hoffentlicht it looks really as good as we had imagined"
| |
| tiles in the guest bathroom |
| |
| Our controlled ventilation system |
| |
| six-corner tub |
Tuesday, December 14, 2010
Green Contacts On Blue Eyes
Elektrovorinstallation
Hello readers,
has started the electric company partners with the Dörbandt Elektrovorinstallation.
We had some time ago a commission with Mr Dörbandt to the positions of light, electricity, establish network and satellite connections. The result is a not altogether insignificant Post at extra cost. We can install the same satellite system and which have a cool-UP Digital Radio by Busch-Jaeger showing:
be mounted in the ceiling then 2 boxes in spot shape.
Well, we have all decided to implement this. Must stop at another place a little to be saved ...
The building owner was on site and has a few final details discussed. Today the wall slots to be created and the next day will be the Cable laid
Hello readers,
has started the electric company partners with the Dörbandt Elektrovorinstallation.
We had some time ago a commission with Mr Dörbandt to the positions of light, electricity, establish network and satellite connections. The result is a not altogether insignificant Post at extra cost. We can install the same satellite system and which have a cool-UP Digital Radio by Busch-Jaeger showing:
| |
| Source: http://www.organiska -elektro.de / |
be mounted in the ceiling then 2 boxes in spot shape.
Well, we have all decided to implement this. Must stop at another place a little to be saved ...
The building owner was on site and has a few final details discussed. Today the wall slots to be created and the next day will be the Cable laid
Sunday, December 12, 2010
Safety Crossword For Science
filling, grinding, grouting and painting
We are done and have (note: self-praise * g *) also accomplished some.
In two weekends we have managed to remove the house completely. They included this unpleasant work such as grinding and filling. Likewise, my favorite task (irony), the Do the expansion joints with acrylic silicone. Luckily, Mario B. has me by email or given the tip that we just have to grout in the EC and the developers working on the first floor makes this lousy - Thanks! :-) Here and there we have
recoating a little, but we do this only if the tiles, etc. in it - the tilers kicks off next Monday. We are very excited about how the rooms appear then. By the white paint the rooms appear much larger and friendlier.
We are done and have (note: self-praise * g *) also accomplished some.
In two weekends we have managed to remove the house completely. They included this unpleasant work such as grinding and filling. Likewise, my favorite task (irony), the Do the expansion joints with acrylic silicone. Luckily, Mario B. has me by email or given the tip that we just have to grout in the EC and the developers working on the first floor makes this lousy - Thanks! :-) Here and there we have
recoating a little, but we do this only if the tiles, etc. in it - the tilers kicks off next Monday. We are very excited about how the rooms appear then. By the white paint the rooms appear much larger and friendlier.
| | |
| white Previously only | |
| |
| After Color |
Epoxy Paint Over Por 15
windows cleaned - Mission Accomplished!
Hello readers,
the effort was worth it ... yesterday within 6 hours, our windows and exterior doors installed. The fitters were full of praise for our previous work. In the living room we could actually reach +18 ° C, not bad, although we have played the mild temperatures also in the cards:
Here are some (bad) pictures:
Click here for more pictures ...
begins on Tuesday the Elektrovorinstallation, heating and medical man should then start it.
Hello readers,
the effort was worth it ... yesterday within 6 hours, our windows and exterior doors installed. The fitters were full of praise for our previous work. In the living room we could actually reach +18 ° C, not bad, although we have played the mild temperatures also in the cards:
Here are some (bad) pictures:
| |
| living |
| |
| living |
Click here for more pictures ...
| |
| door HWR |
| |
| HWR |
| |
| guest toilet |
| |
| kitchen |
| |
| dining |
| |
| door with vorläüfiger filling |
begins on Tuesday the Elektrovorinstallation, heating and medical man should then start it.